May 22, 2008
T-minus 3 days

T-minus 3 days. That's all the time that is left until we land.

Management put a stop to all testing this week, so we were been busy running simulations and tests on the hardware all last week.

The first week on Mars will be characterizing the instruments, and we need all those blocks tested before we land. Some teams are doing better than others.

The TEGA team was here several days for testing blocks that will be run after the first week on Mars, so they're ahead of the game. I spent a lot of time running blocks for the RAC team that needed to be done by last Friday.

Even though this week we're not supposed to be testing, we are running a few tests. That's not really surprising. But the quantity has dropped, so I've been taking some vacation time.

Next week, I start my Mars schedule. Four days on, three off, following the Mars Sol (or day) which is 40 minutes longer than an Earth day. This can really throw one off. We'll see how it goes.

Three days determine everyone's future. Whether I still have a job. If we'll do any science. Will anyone get to see a picture from Mars?

I've been working on the project for 2 and one-half years. Others for upwards of six, including the original proposal to NASA. I remember when our countdown timer read 500-plus days until launch. Now it reads three days until we land on another planet.

Kinda cool, isn't it?

Posted at 02:30 PM

E-mail this entry to a friend

Comments

Hard to believe this is the sixth Mars landing.

Let's set off a string of nukes, dust the planet with plant spores and let the terraforming process begin!

Posted by kitkat
May 22, 2008 03:34 PM

http://phoenix.lpl.arizona.edu/news.php

http://mars.jpl.nasa.gov/

http://www.nasa.gov/mission_pages/phoenix/main/index.html

Posted by current news and images
May 27, 2008 03:08 PM

Post a comment









Remember personal info?







Please enter the code as seen in the image above:



Blog Index

A native Mainer writes about his experiences as an engineer for the Phoenix Mars Mission, an effort to see if a robotic lander can find evidence that life once existed on Mars.

Robert Bovill was born at Maine Medical Center July 5, 1979. He graduated from Thornton Academy in 1998. He graduated with a bachelor's degree in physics from the University of Maine in Orono, and then went to the University of Arizona for graduate school. He was employed full-time as a test engineer for this Phoenix Mars Mission a year and a half ago by the University of Arizona.



See a rendering of the Phoenix Mars lander during the final seconds of descent.

See the instruments on the Phoenix Mars lander.

Abbreviation Glossary

Testing  
FVT   Functional Verification Test
GDS   Ground Data System
OPUS Odyssey/Phoenix UHF System
ORT Operational Readiness Test/Training
PIT    Payload Inter-operability Testbed
PTL Payload Testbed Lab
PVV Payload Verification and Validation
   
Places  
JPL  Jet Propulsion Laboratory
LM  Lockheed-Martin
UA/LPL University of Arizona/Lunar and Planetary Lab
   
Events
EDL  Entry, Descent and Landing
   
Instruments
EM  Enginerring Model
FM Flight Model
ISAD Icy Sample Acquisition Device
MECA Microscopy, Electrochemistry, and Conductivity Analyzer
OM Optical Microscope
RA Robotic Arm
RAC Robotic Arm Camera
RASP Rapid Active Sampling Package
SSI    Surface Stereoscopic Imager
TECP   Thermal and Electrical Conductivity Probe
TEGA  Thermal and Evolved Gas Analyzer
Updates
Sign up to be notified when there's a new entry
RSS
Subscribe
Archives